Feature #15531
Update plans and timeline wrt. upgrading to Tor Browser based on Firefox 60ESR
Start date:
2018-04-13
Due date:
2018-07-06
% Done:
100%
Description
We shall do that end of May and then again end of June.
Subtasks
Related issues
Blocked by Tails - |
Rejected | 2018-04-13 | |
Blocks Tails - |
Resolved | 2018-02-20 |
History
#1 Updated by intrigeri 2018-04-13 12:45:18
- blocked by
Feature #15530: Start upgrading to Tor Browser based on Firefox ESR60 added
#2 Updated by intrigeri 2018-04-13 12:45:52
- Description updated
#3 Updated by intrigeri 2018-04-13 12:46:29
- blocks
Feature #15139: Core work 2018Q2: Foundations Team added
#4 Updated by intrigeri 2018-05-26 09:46:41
- Priority changed from Normal to Elevated
#5 Updated by intrigeri 2018-05-28 14:47:14
For now I’m leaving Feature #15530 on anonym’s plate (he wants one FT ticket on his plate). Depending on the progress in a month we’ll keep it this way or I’ll share this work with segfault.
#6 Updated by intrigeri 2018-05-28 14:48:08
- Status changed from Confirmed to In Progress
- % Done changed from 0 to 20
#7 Updated by intrigeri 2018-06-03 07:46:34
- Due date set to 2018-06-28
- Priority changed from Elevated to High
- Target version changed from Tails_3.8 to Tails_3.9
The decision will be made at the FT meeting on June 28 i.e. 2 days after the 3.8 release.
#8 Updated by intrigeri 2018-06-28 14:22:53
We’ll make plans on 2018-07-03, 16:00 CEST.
#9 Updated by intrigeri 2018-06-28 14:22:58
- blocked by deleted (
)Feature #15139: Core work 2018Q2: Foundations Team
#10 Updated by intrigeri 2018-06-28 14:23:02
- blocks
Feature #15334: Core work 2018Q3: Foundations Team added
#11 Updated by intrigeri 2018-06-30 16:36:02
- Due date changed from 2018-06-28 to 2018-07-03
#12 Updated by intrigeri 2018-07-03 13:54:53
- Due date changed from 2018-07-03 to 2018-07-04
We have a plan! I still need 2 bits of info to be 100% confident in this plan:
- will we have to deal with Tor Launcher XUL ext disappearing? (
Bug #14555) - does the test suite expose big issues? (
Feature #15701)
I’ll try to gather the answers by tomorrow night.
#13 Updated by intrigeri 2018-07-05 15:27:19
- Due date changed from 2018-07-04 to 2018-07-06
#14 Updated by intrigeri 2018-07-10 15:56:29
- Status changed from In Progress to Resolved
- Assignee deleted (
intrigeri) - % Done changed from 20 to 100
Things seem to be under control so unless crazy shit happens our plan should work :)