Come up with a budget and calendar to migrate DAVE to Web Extensions
Start date:
2017-07-31
Due date:
% Done:
0%
Description
- Calendar: Everything has to be done before November 14.
- Budget: We don’t have a specific budget for this but we need an initial proposal from the workers before being able to decide where the money would come from.
Subtasks
History
#1 Updated by sajolida 2017-07-31 11:57:33
- Assignee changed from sajolida to anonym
I sent a proposal to Uzair and anonym on July 14, the ball is now on anonym’s side.
#2 Updated by anonym 2017-08-17 11:57:54
- Assignee changed from anonym to sajolida
Passing the ball (given our email exchanges)!
#3 Updated by sajolida 2017-09-05 09:52:24
- Status changed from Confirmed to Resolved
- Assignee deleted (
sajolida)
We did that on tails@boum.org and the budget was discussed and approved.
#4 Updated by intrigeri 2017-12-16 07:37:07
- Affected tool deleted (
Download and Verification Extension)