Bug #10615
Reevaluate time estimates of installation scenarios
Start date:
2015-11-24
Due date:
% Done:
0%
Description
Subtasks
Related issues
Blocks Tails - |
Resolved | 2015-11-24 |
History
#1 Updated by sajolida 2015-11-24 02:47:23
- Parent task set to
Feature #8590
#2 Updated by intrigeri 2015-11-24 06:14:01
May you please give this ticket a less generic title? Thanks!
#3 Updated by sajolida 2015-11-27 07:22:46
- Subject changed from Reevaluate time estimates to Reevaluate time estimates of installation scenarios
Less generic ticket name. Sorry for that, I made sure to attribute a parent tickets for all of our new tickets on the Installation Assistant and I thought this was a good way of differentiating them.
#4 Updated by sajolida 2015-12-11 14:06:38
- Assignee changed from sajolida to tchou
- QA Check set to Ready for QA
Most of our tests lasted more than a hour (about 1h10-1h20 in general). Some people did a bit more than a scenario but we also provided then with a shorter than usual download. So I’d like to be less precise in general (talk about “hours” instead of “minutes”) and round everything up a bit.
It could be:
| scenario | old | new |
|---------------+-----+-----|
| upgrade clone | 10 | 1/4 |
| upgrade Tails | 20 | 1/2 |
| install clone | 15 | 1/2 |
| windows usb | 45 | 1 |
| linux usb | 45 | 1 |
| debian usb | 25 | 1/2 |
| mac dvd | 45 | 1 |
| mac usb | 45 | 1 |
#5 Updated by tchou 2015-12-12 03:23:24
- Assignee changed from tchou to sajolida
- QA Check changed from Ready for QA to Pass
#6 Updated by sajolida 2015-12-16 09:47:45
- Target version changed from Tails_1.8 to Tails_2.0
- QA Check changed from Pass to Dev Needed
Now I need to implement this.
#7 Updated by tchou 2015-12-16 09:57:41
- blocks
Feature #10628: More consistency in needs between router and overview added
#8 Updated by tchou 2015-12-16 09:58:12
I mark Feature #10628 as blocked by this one.
#9 Updated by sajolida 2016-01-05 17:39:31
- Parent task changed from
Feature #8590toFeature #8592
#10 Updated by sajolida 2016-01-05 17:49:25
- blocked by deleted (
)Feature #10628: More consistency in needs between router and overview
#11 Updated by sajolida 2016-01-05 17:50:24
- blocks
Feature #10628: More consistency in needs between router and overview added
#12 Updated by sajolida 2016-01-05 21:54:46
- Priority changed from Normal to Elevated
#13 Updated by sajolida 2016-01-12 15:02:53
- Assignee changed from sajolida to tchou
- QA Check changed from Dev Needed to Ready for QA
- Feature Branch set to web/10615-reevaluate-time-estimates
Done in f85111f. I also further simplify everything with 540be5a.
#14 Updated by tchou 2016-01-13 15:31:03
- Assignee deleted (
tchou) - QA Check changed from Ready for QA to Pass
#15 Updated by sajolida 2016-01-15 13:43:57
- Status changed from Confirmed to Resolved
- QA Check deleted (
Pass)